Flashcards #5
Click the card to flip it 👇
What is the maximum diversion rate allowed for unverified commingled recycling?
35% diversion rate.
What materials are excluded from diversion calculations?
Hazardous waste, excavated soil, and land-clearing debris.
What is alternative daily cover (ADC)?
Material such as soil used to cover landfill waste daily; not counted as diversion.
How are salvaged materials valued in MRc5 diversion calculations?
Valued at 200% of their weight or volume.
What does EQp1 Construction Management require regarding smoking?
Prohibit smoking except in designated areas at least 25 feet (7.5 meters) from the building.
What protective measure is required for construction workers under EQp1?
Implement measures to protect construction workers from extreme heat.
What must be done with HVAC systems during construction under EQp1?
Keep contaminants out of HVAC, never run equipment without filtration, confirm testing and balancing with new filters, replace filters before occupancy.
What materials must be protected from moisture damage under EQp1?
Carpets, acoustical ceiling panels, fabric coverings, insulation, and furnishings.
What is required to prevent contaminated air circulation under EQp1?
Seal doorways and windows, use walk-off mats, and apply dust guards and collectors on tools.
What is the housekeeping requirement under EQp1?
Maintain a clean jobsite with efficient vacuums and sweeping compounds or wetting agents.
Nice work!
You just studied 10 terms!
Start over
For all 500 cards, get the full deck:
500 LEED AP BD+C Flashcards
- 500 LEED AP BD+C v5 flashcards
- Digital and printable PDF
- Study on the go on any device
- On-demand instructor support
- 12-month access